Calculation Methodology

Design event: 10-year (10% AEP)

Method: Site-Specific Design

Gisborne is a unitary authority. The piped system is designed for the 10-year storm event. Site-specific assessment is required via resource consent.

Design Requirements

  • 10% AEP (10-year) piped system design
  • Site-specific assessment via resource consent

Submission

Required Documents

  • Stormwater design report
  • Engineering plans
  • Resource consent