New Plymouth District Council

Stormwater Detention & Retention Requirements

Taranaki Region

Source Documents

These are the council documents used to build the NPDC calculator. If a link is broken, the document may have moved on the council website.

📄
Land Development and Subdivision Infrastructure Standard (Local Amendments v3)
PDF Primary Source

Calculation Methodology

Design event: 10-year (10% AEP)

Method: On-Site Disposal Required

New Plymouth's primary requirement is on-site disposal. Soakpits, swales, basins, or rainwater tanks are the preferred approach. Connection to the council stormwater network is only permitted where no on-site option is available.

New Plymouth, Stratford, and South Taranaki share the Taranaki Land Development standard.

Design Requirements

  • On-site disposal is the primary requirement
  • Soakpits, swales, basins, or rainwater tanks
  • Connection to council network only as last resort
  • Shared Taranaki standard with Stratford + South Taranaki

Submission

Required Documents

  • Site-specific stormwater design
  • Soakage test results
  • Engineering plans
  • Resource consent (if applicable)

Contact

Phone(06) 759 6060
RegionTaranaki