Tasman District Council

Stormwater Detention & Retention Requirements

Nelson/Tasman Region

Source Documents

These are the council documents used to build the TDC calculator. If a link is broken, the document may have moved on the council website.

📄
Nelson Tasman Land Development Manual (NTLDM) 2020
PDF Primary Source

Calculation Methodology

Design event: 100-year (1% AEP)

Method: Rational Method (NTLDM)

Tasman shares the Nelson Tasman Land Development Manual with Nelson City Council. Post-development peak flows for 10yr, 20yr, and 100yr ARI must not exceed pre-development at critical downstream locations. On-site tanks: lower 2/3 for reuse, upper 1/3 for detention.

CPEng certification required for detention basins and dams. Consent notice on property title required.

Design Requirements

  • 10yr, 20yr, 100yr ARI - post-dev <= pre-dev at critical downstream
  • 1% AEP floodway design
  • Rational Method: Q = C x I x A x 2.78 (L/s)
  • C values from NTLDM Table 7-4 with slope correction
  • On-site tanks: 2/3 reuse (lower), 1/3 detention (upper)
  • Extended detention: 24hr drawdown
  • CPEng certification required for detention basins/dams
  • Consent notice (RMA s221) on property title

Submission

Required Documents

  • Catchment plan and hydrological analysis
  • Detention sizing for 10yr, 20yr, 100yr ARI
  • Resource consent copies
  • Maintenance plan
  • CPEng design certificate (basins/dams)
  • Manufacturer's tank specifications